If a switch port receives a new frame while it is actively transmitting a previous frame, how does it process the frames?

A.
The new frame is delivered first, the previous frame is dropped, and a retransmission request is sent
B. The previous frame is delivered, the new frame is dropped, and a retransmission request is sent
C. The new frame is placed in a queue for transmission after the previous frame
D. The two frames are processed and delivered at the same time

Correct Answer: C