CGEIT Certified in the Governance of Enterprise IT – Question086

The IT director of a large project-driven enterprise is concerned that all recently completed IT projects have exceeded their budgets. Which of the following would be the BEST way to address this concern?

A.
Implement portfolio management.
B. Require monitoring of budget utilization.
C. Assign business sponsors to active projects.
D. Implement agile project methodology.

Correct Answer: B