CGEIT Certified in the Governance of Enterprise IT – Question258

A rail transport company has the worst on-time arrival record in the industry due to an antiquated IT system that controls scheduling. Despite employee resistance, an initiative to upgrade the technology and related processes has been approved. To maximize employee engagement throughout the project, which of the following should be in place prior to the start of the initiative?

A.
Procurement management plan
B. Risk response plan
C. Organizational change management plan
D. Resource management plan

Correct Answer: C