A strategic systems project was implemented several months ago. Which of the following is the BEST reference for the IT steering committee as they evaluate its level of success?
A. The project's business case
B. Stakeholder satisfaction surveys
C. The project's net present value (NPV)
D. Operating metrics of the new system
A. The project's business case
B. Stakeholder satisfaction surveys
C. The project's net present value (NPV)
D. Operating metrics of the new system