CISA Certified Information Systems Auditor – Question1907

For application acquisitions with significant impacts, participation of your IS audit team should be encouraged:

A.
early in the due diligence stage.
B. at the testing stage.
C. at the final approval stage.
D. at the budget preparation stage.
E. None of the choices.

Correct Answer: A

Explanation:

Explanation:
For acquisitions with significant IT impacts, participation of IS audit is often necessary early in the due diligence stage as defined in the audit policy.