CISA Certified Information Systems Auditor – Question2330

With the objective of mitigating the risk and impact of a major business interruption, a disaster recovery plan should endeavor to reduce the length of recovery time necessary, as well as costs associated with recovery. Although DRP results in an increase of preand post-incident operational costs, the extra costs are more than offset by reduced recovery and business impact costs. True or false?

A.
True
B. False

Correct Answer: A

Explanation:

Explanation:
With the objective of mitigating the risk and impact of a major business interruption, a disaster- recovery plan should endeavor to reduce the length of recovery time necessary and the costs associated with recovery. Although DRP results in an increase of preand post-incident operational costs, the extra costs are more than offset by reduced recovery and business impact costs.