CISA Certified Information Systems Auditor – Question0233

Management has agreed to perform multiple remediation actions in response to an audit issue, including the implementation of a new control. Which of the following is the BEST time for an IS auditor to perform an audit follow-up of this issue?

A.
After management has completed the required actions
B. When audit resources are available
C. When management resources are available
D. After the new control has been in place for one year

Correct Answer: A