CISA Certified Information Systems Auditor – Question2892

Following best practices, formal plans for implementation of new information systems are developed during the:

A.
development phase.
B. design phase.
C. testing phase.
D. deployment phase.

Correct Answer: B

Explanation:

Explanation:
Planning for implementation should begin well in advance of the actual implementation date. A formal implementation plan should be constructed in the design phase and revised as the development progresses.