CISA Certified Information Systems Auditor – Question0742

When conducting a requirements analysis for a project the BEST approach would be to:

A.
conduct a control self-assessment.
B. consult key stakeholders.
C. test operational deliverables.
D. prototype the requirements.

Correct Answer: B