CISA Certified Information Systems Auditor – Question0772

The PRIMARY responsibility of a project steering committee is to:

A.
ensure that each project deadline is met
B. undertake final acceptance of the system for implementation
C. ensure that systems developed meet business needs
D. provide day-to-day guidance and oversight

Correct Answer: D