When planning for the implementation of a new system, an organization will opt for a parallel run PRIMARILY to:
A. ensure that the system meets required user response time.
B. validate system processing.
C. facilitate the training of new personnel.
D. verify that system interfaces were implemented.
A. ensure that the system meets required user response time.
B. validate system processing.
C. facilitate the training of new personnel.
D. verify that system interfaces were implemented.