The MOST important factors in determining the scope and timing for testing a business continuity plan are:

A.
manual processing capabilities and the test location.
B. the importance of the function to be tested and the cost of testing.
C. the experience level of personnel and the function location.
D. prior testing results and the degree of detail of the business continuity plan.

Correct Answer: B