CISA Certified Information Systems Auditor – Question0833

Which of the following is MOST important in determining a project’s feasibility?

A.
The organization’s main competitor has initiated a similar project.
B. The IT steering committee endorses the project.
C. A project management methodology is established.
D. The project’s value is established in an approved business case.

Correct Answer: D