CISA Certified Information Systems Auditor – Question0851

A company is using a software developer for a project. At which of the following points should the software quality assurance (QA) plan be developed?

A.
As part of software definition
B. During the feasibility phase
C. Prior to acceptance testing
D. As part of the design phase

Correct Answer: D