CISA Certified Information Systems Auditor – Question0982

An IS auditor finds that the cost of developing an application is now projected to significantly exceed the budget. Which of the following is the GREATEST risk to communicate to senior management?

A.
Increased staff turnover
B. Project abandonment
C. Noncompliance with project methodology
D. Inability to achieve expected benefits

Correct Answer: B