CISA Certified Information Systems Auditor – Question0071

An IS auditor has completed an audit on the organization’s IT strategic planning process. Which of the following findings should be given the HIGHEST priority?

A.
The IT strategic plan was completed prior to the formulation of the business strategic plan
B. Assumptions in the IT strategic plan have not been communicated to business stakeholders
C. The IT strategic plan was formulated based on the current IT capabilities
D. The IT strategic plan does not include resource requirements for implementation

Correct Answer: A