CISA Certified Information Systems Auditor – Question0161

When evaluating whether the expected benefits of a project have been achieved, it is MOST important for an IS auditor to review:

A.
post-implementation issues.
B. quality assurance results.
C. the project schedule.
D. the business case.

Correct Answer: D