CISA Certified Information Systems Auditor – Question0255

Which of the following should be of GREATEST concern to an IS auditor when evaluating a new system’s production readiness?

A.
A system defect was found during user acceptance testing.
B. Functional design documentation is not complete.
C. Functional requirements have not been met.
D. Projected benefits have not been realized.

Correct Answer: C