CISA Certified Information Systems Auditor – Question0289

The scheduling of audit follow-ups should be based PRIMARILY on:

A.
costs and audit efforts involved.
B. auditee and auditor time commitments.
C. the risk and exposure involved.
D. control and detection processes.

Correct Answer: C