CISA Certified Information Systems Auditor – Question0567

Which of the following can provide assurance that an IT project has delivered its planned benefits?

A.
User acceptance testing (UAT)
B. Steering committee approval
C. Post-implementation review
D. Quality assurance evaluation

Correct Answer: C