What is the BEST method to determine if IT resource spending is aligned with planned project spending?
A. Earned value analysis (EVA)
B. Gantt chart
C. Return on investment (ROI) analysis
D. Critical path analysis
A. Earned value analysis (EVA)
B. Gantt chart
C. Return on investment (ROI) analysis
D. Critical path analysis