The PRIMARY objective of conducting a post-implementation review is to:

A.
determine if project management methodology was applied consistently
B. verify that the information system meets the intended objectives
C. determine if testing documentation was sufficient
D. allow employees to provide feedback on the information system

Correct Answer: B