During the procurement process, which of the following would be the BEST indication that prospective vendors will meet the organization’s needs?
A. An account transition manager has been identified.
B. Expected service levels are defined.
C. The vendor’s subcontractors have been identified.
D. The service catalog is documented.
A. An account transition manager has been identified.
B. Expected service levels are defined.
C. The vendor’s subcontractors have been identified.
D. The service catalog is documented.