The PRIMARY reason for allocating sufficient time between the “go-live” phase of a new system and conducting a post-implementation review is to:
A. update project requirements and design documentation
B. increase availability of system implementation team resources
C. allow the system to stabilize in production
D. obtain sign-off on the scope of post-implementation review
A. update project requirements and design documentation
B. increase availability of system implementation team resources
C. allow the system to stabilize in production
D. obtain sign-off on the scope of post-implementation review