CISA Certified Information Systems Auditor – Question0862

A change to the scope of an IT project has been formally submitted to the project manager. What should the project manager do NEXT?

A.
Update the project plan to reflect the change in scope
B. Discuss the change with the project team and determine if it should be approved
C. Escalate the change to the change advisory board for approval
D. Determine how the change will affect the schedule and budget

Correct Answer: B