Following request for proposal (RFP) responses, a project seeking to acquire a new application system has identified a short list of vendors. At this point, the IS auditor should:

A.
encourage contact with current users of the vendor’s products
B. perform a detailed cost-benefit exercise on the proposed application
C. require that contract terms include a right-to-audit clause
D. recommend performing system integration tests

Correct Answer: C