CISA Certified Information Systems Auditor – Question0992

Which of the following is MOST important for the successful completion of a new application system?

A.
Appropriate training of system analysts
B. Steering committee approval of the new system
C. Completion of a positive cost-benefit analysis
D. User participation in the project development

Correct Answer: B