After implementation of a disaster recovery plan, pre-disaster and post-disaster operational costs for an organization will:

A.
decrease.
B. not change (remain the same).
C. increase.
D. increase or decrease depending upon the nature of the business.

Correct Answer: C

Explanation:

Explanation:
There are costs associated with all activities and disaster recovery planning (DRP) is not an exception. Although there are costs associated with a disaster recovery plan, there are unknown costs that are incurred if a disaster recovery plan is not implemented.