CISA Certified Information Systems Auditor – Question1756

The PRIMARY objective of testing a business continuity plan is to:

A.
familiarize employees with the business continuity plan.
B. ensure that all residual risks are addressed.
C. exercise all possible disaster scenarios.
D. identify limitations of the business continuity plan.

Correct Answer: D

Explanation:

Explanation:
Testing the business continuity plan provides the best evidence of any limitations that may exist. Familiarizing employees with the business continuity plan is a secondary benefit of a test. It is not cost effective to address residual risks in a business continuity plan, and it is not practical to test all possible disaster scenarios.