CISA Certified Information Systems Auditor – Question1768

The activation of an enterprise's business continuity plan should be based on predetermined criteria that address the:

A.
duration of the outage.
B. type of outage.
C. probability of the outage.
D. cause of the outage.

Correct Answer: A

Explanation:

Explanation:
The initiation of a business continuity plan (action) should primarily be based on the maximum period for which a business function can be disrupted before the disruption threatens the achievement of organizational objectives.