CISA Certified Information Systems Auditor – Question1811

Which of the following is MOST likely to result from a business process reengineering (BPR) project?

A.
An increased number of people using technology
B. Significant cost savings, through a reduction in the complexity of information technology
C. A weaker organizational structures and less accountability
D. Increased information protection (IP) risk will increase

Correct Answer: A

Explanation:

Explanation:
A BPR project more often leads to an increased number of people using technology, and this would be a cause for concern. Incorrect answers:
(B.) As BPR is often technology oriented, and this technology is usually more complex and volatile than in the past, cost savings do not often materialize in this area.
(D.) There is no reason for IP to conflict with a BPR project, unless the project is not run properly.