CISA Certified Information Systems Auditor – Question1931

A new system development project is running late against a critical implementation deadline. Which of the following is the MOST important activity?

A.
Document last-minute enhancements.
B. Perform user acceptance testing.
C. Perform a pre-implementation audit.
D. Ensure that code has been reviewed.

Correct Answer: D