In planning a major system development project, function point analysis would assist in:

A.
estimating the elapsed time of the project.
B. estimating the size of a system development task.
C. analyzing the functions undertaken by system users as an aid to job redesign.
D. determining the business functions undertaken by a system or program.

Correct Answer: C