CISA Certified Information Systems Auditor – Question1943

The business case for an IS project has changed during the course of the project due to new requirements being added. What should be done NEXT?

A.
The project should go through the formal reapproval process.
B. The changes to the business case should be documented in the project plan.
C. Additional resources should be allocated to the project due to the new requirements.
D. Project stakeholders should be notified of the changes.

Correct Answer: D