CISA Certified Information Systems Auditor – Question1971

One advantage of managing an entire collection of projects as a portfolio is that it highlights the need to:

A.
identify dependencies between projects.
B. inform users about all ongoing projects.
C. manage the risk of each individual project.
D. manage the quality of each project.

Correct Answer: D