Reviewing project plans and status reports throughout the development life cycle will:

A.
eliminate the need to perform a risk assessment.
B. postpone documenting the project’s progress until the final phase.
C. guarantee that the project will meet its intended deliverables.
D. facilitate the optimal use of resources over the life of the project.

Correct Answer: D