CISA Certified Information Systems Auditor – Question2039

A purpose of project closure is to determine the:

A.
potential risks affecting the quality of deliverables.
B. lessons learned for use in future projects.
C. project feasibility requirements
D. professional expertise of the project manager.

Correct Answer: B