What is a primary high-level goal for an auditor who is reviewing a system development project?
A. To ensure that programming and processing environments are segregated
B. To ensure that proper approval for the project has been obtained
C. To ensure that business objectives are achieved
D. To ensure that projects are monitored and administrated effectively
A. To ensure that programming and processing environments are segregated
B. To ensure that proper approval for the project has been obtained
C. To ensure that business objectives are achieved
D. To ensure that projects are monitored and administrated effectively