CISA Certified Information Systems Auditor – Question2343

If an IS auditor observes that individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further:

A.
Documentation development
B. Comprehensive integration testing
C. Full unit testing
D. Full regression testing

Correct Answer: B

Explanation:

Explanation:
If an IS auditor observes individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further comprehensive integration testing.