CISA Certified Information Systems Auditor – Question2390

What often results in project scope creep when functional requirements are not defined as well as they could be?

A.
Inadequate software baselining
B. Insufficient strategic planning
C. Inaccurate resource allocation
D. Project delays

Correct Answer: A

Explanation:

Explanation:
Inadequate software baselining often results in project scope creep because functional requirements are not defined as well as they could be.