CISA Certified Information Systems Auditor – Question2489

Who is responsible for the overall direction, costs, and timetables for systems-development projects?

A.
The project sponsor
B. The project steering committee
C. Senior management
D. The project team leader

Correct Answer: B

Explanation:

Explanation:
The project steering committee is responsible for the overall direction, costs, and timetables for systems-development projects.