Which of the following is a benefit of a risk-based approach to audit planning? Audit:
A. scheduling may be performed months in advance.
B. budgets are more likely to be met by the IS audit staff.
C. staff will be exposed to a variety of technologies.
D. resources are allocated to the areas of highest concern
A. scheduling may be performed months in advance.
B. budgets are more likely to be met by the IS audit staff.
C. staff will be exposed to a variety of technologies.
D. resources are allocated to the areas of highest concern