CISA Certified Information Systems Auditor – Question2685

Which of the following should be performed FIRST when preparing to deploy a major upgrade to a critical online application?

A.
Update the disaster recovery process.
B. Update the business impact analysis (BIA).
C. Test the rollback process.
D. Review data backup procedures.

Correct Answer: C