CISA Certified Information Systems Auditor – Question2759

Which of the following BEST supports the prioritization of new IT projects?

A.
Internal control self-assessment (CSA)
B. Information systems audit
C. Investment portfolio analysis
D. Business risk assessment

Correct Answer: C

Explanation:

Explanation:
It is most desirable to conduct an investment portfolio analysis, which will present not only a clear focus on investment strategy, but will provide the rationale for terminating nonperforming IT projects. Internal control self-assessment (CSA) may highlight noncompliance to the current policy, but may not necessarily be the best source for driving the prioritization of IT projects. Like internal CSA, IS audits may provide only part of the picture for the prioritization of IT projects.
Business risk analysis is part of the investment portfolio analysis but, by itself, is not the best method for prioritizing new IT projects.