Change control for business application systems being developed using prototyping could be complicated by the:
A. iterative nature of prototyping.
B. rapid pace of modifications in requirements and design.
C. emphasis on reports and screens.
D. lack of integrated tools.
A. iterative nature of prototyping.
B. rapid pace of modifications in requirements and design.
C. emphasis on reports and screens.
D. lack of integrated tools.