CISA Certified Information Systems Auditor – Question2822

An IS auditor has been asked to participate in project initiation meetings for a critical project. The IS auditor's MAIN concern should be that the:

A.
complexity and risks associated with the project have been analyzed.
B. resources needed throughout the project have been determined.
C. project deliverables have been identified.
D. a contract for external parties involved in the project has been completed.

Correct Answer: A

Explanation:

Explanation:
Understanding complexity and risk, and actively managing these throughout a project are critical to a successful outcome. The other choices, while important during the course of the project, cannot be fully determined at the time the project is initiated, and are often contingent upon the risk and complexity of the project.