When two or more systems are integrated, input/output controls must be reviewed by an IS auditor in the:

A.
systems receiving the output of other systems.
B. systems sending output to other systems.
C. systems sending and receiving data.
D. interfaces between the two systems.

Correct Answer: C

Explanation:

Explanation:
Both of the systems must be reviewed for input/output controls, since the output for one system is the input for the other.