The recovery time objective (RTO) is normally determined on the basis of the:
A. criticality of the systems affected
B. risk of occurrence
C. acceptable downtime of the alternate site
D. cost of recovery of all systems
A. criticality of the systems affected
B. risk of occurrence
C. acceptable downtime of the alternate site
D. cost of recovery of all systems