CISA Certified Information Systems Auditor – Question2828

When reviewing an active project, an IS auditor observed that, because of a reduction in anticipated benefits and increased costs, the business case was no longer valid. The IS auditor should recommend that the:

A.
project be discontinued.
B. business case be updated and possible corrective actions be identified.
C. project be returned to the project sponsor for reapproval.
D. project be completed and the business case be updated later.

Correct Answer: B

Explanation:

Explanation: An IS auditor should not recommend discontinuing or completing the project before reviewing an updated business case. The IS auditor should recommend that the business case be kept current throughout the project since it is a key input to decisions made throughout the life of any project.

CISA Certified Information Systems Auditor – Question2827

Which of the following should an IS auditor review to understand project progress in terms of time, budget and deliverables for early detection of possible overruns and for projecting estimates at completion (EACs)?

A.
Function point analysis
B. Earned value analysis
C. Cost budget
D. Program Evaluation and Review Technique

Correct Answer: B

Explanation:

Explanation:
Earned value analysis (EVA) is an industry standard method for measuring a project’s progress at any given point in time, forecasting its completion date and final cost, and analyzing variances in the schedule and budget as the project proceeds. It compares the planned amount of work with what has actually been completed, to determine if the cost, schedule and work accomplished are progressing in accordance with the plan. EVA works most effectively if a well-formed work breakdown structure exists. Function point analysis (FPA) is an indirect measure of software size and complexity and, therefore, does not address the elements of time and budget. Cost budgets do not address time. PERT aids in time and deliverables management, but lacks projections for estimates at completion (EACs) and overall financial management.

CISA Certified Information Systems Auditor – Question2826

An IS auditor is assigned to audit a software development project which is more than 80 percent complete, but has already overrun time by 10 percent and costs by 25 percent. Which of the following actions should the IS auditor take?

A.
Report that the organization does not have effective project management.
B. Recommend the project manager be changed.
C. Review the IT governance structure.
D. Review the conduct of the project and the business case.

Correct Answer: D

Explanation:

Explanation:
Before making any recommendations, an IS auditor needs to understand the project and the factors that have contributed to making the project over budget and over schedule. The organization may have effective project management practices and sound IT governance and still be behind schedule or over budget. There is no indication that the project manager should be changed without looking into the reasons for the overrun.

CISA Certified Information Systems Auditor – Question2825

When reviewing a project where quality is a major concern, an IS auditor should use the project management triangle to explain that:

A.
increases in quality can be achieved, even if resource allocation is decreased.
B. increases in quality are only achieved if resource allocation is increased.
C. decreases in delivery time can be achieved, even if resource allocation is decreased.
D. decreases in delivery time can only be achieved if quality is decreased.

Correct Answer: A

Explanation:

Explanation:
The three primary dimensions of a project are determined by the deliverables, the allocated resources and the delivery time. The area of the project management triangle, comprised of these three dimensions, is fixed. Depending on the degree of freedom, changes in one dimension might be compensated by changing either one or both remaining dimensions. Thus, if resource allocation is decreased an increase in quality can be achieved, if a delay in the delivery time of the project will be accepted. The area of the triangle always remains constant.

CISA Certified Information Systems Auditor – Question2824

While evaluating software development practices in an organization, an IS auditor notes that the quality assurance (QA) function reports to project management. The MOST important concern for an IS auditor is the:

A.
effectiveness of the QA function because it should interact between project management and user management
B. efficiency of the QA function because it should interact with the project implementation team.
C. effectiveness of the project manager because the project manager should interact with the QA function.
D. efficiency of the project manager because the QA function will need to communicate with the project implementation team.

Correct Answer: A

Explanation:

Explanation:
To be effective the quality assurance (QA) function should be independent of project management. The QA function should never interact with the project implementation team since this can impact effectiveness. The project manager does not interact with the
QA function, which should not impact the effectiveness of the project manager. The QA function does not interact with the project implementation team, which should not impact the efficiency of the project manager.

CISA Certified Information Systems Auditor – Question2823

An IS auditor invited to a development project meeting notes that no project risks have been documented. When the IS auditor raises this issue, the project manager responds that it is too early to identify risks and that, if risks do start impacting the project, a risk manager will be hired. The appropriate response of the IS auditor would be to:

A.
stress the importance of spending time at this point in the project to consider and document risks, and to develop contingency plans.
B. accept the project manager's position as the project manager is accountable for the outcome of the project.
C. offer to work with the risk manager when one is appointed.
D. inform the project manager that the IS auditor will conduct a review of the risks at the completion of the requirements definition phase of the project.

Correct Answer: A

Explanation:

Explanation: the majority of project risks can typically be identified before a project begins, allowing mitigation/avoidance plans to be put in place to deal with the risks. A project should have a clear link back to corporate strategy and tactical plans to support this strategy. The process of setting corporate strategy, setting objectives and developing tactical plans should include the consideration of risks. Appointing a risk manager is a good practice but waiting until the project has been impacted by risks is misguided. Risk management needs to be forward looking; allowing risks to evolve into issues that adversely impact the project represents a failure of risk management. With or without a risk manager, persons within and outside of the project team need to be consulted and encouraged to comment when they believe new risks have emerged or risk priorities have changed. The IS auditor has an obligation to the project sponsor and the organization to advise on appropriate project manage me practices. Waiting for the possible appointment of a risk manager represents an unnecessary and dangerous delay to implementing risk management.

CISA Certified Information Systems Auditor – Question2822

An IS auditor has been asked to participate in project initiation meetings for a critical project. The IS auditor's MAIN concern should be that the:

A.
complexity and risks associated with the project have been analyzed.
B. resources needed throughout the project have been determined.
C. project deliverables have been identified.
D. a contract for external parties involved in the project has been completed.

Correct Answer: A

Explanation:

Explanation:
Understanding complexity and risk, and actively managing these throughout a project are critical to a successful outcome. The other choices, while important during the course of the project, cannot be fully determined at the time the project is initiated, and are often contingent upon the risk and complexity of the project.

CISA Certified Information Systems Auditor – Question2821

At the completion of a system development project, a post project review should include which of the following?

A.
Assessing risks that may lead to downtime after the production release
B. Identifying lessons learned that may be applicable to future projects
C. Verifying the controls in the delivered system are working
D. Ensuring that test data are deleted

Correct Answer: B

Explanation:

Explanation:
A project team has something to learn from each and every project. As risk assessment is a key issue for project management, it is important for the organization to accumulate lessons learned and integrate them into future projects. An assessment of potential downtime should be made with the operations group and other specialists before implementing a system. Verifying that controls are working should be covered during the acceptance test phase and possibly, again, in the post implementation review. Test data should be retained for future regression testing.

CISA Certified Information Systems Auditor – Question2820

When identifying an earlier project completion time, which is to be obtained by paying a premium for early completion, the activities that should be selected are those:

A.
whose sum of activity time is the shortest.
B. that have zero slack time.
C. that give the longest possible completion time.
D. whose sum of slack time is the shortest.

Correct Answer: B

Explanation:

Explanation:
A critical path’s activity time is longer than that for any other path through the network. This path is important because if everything goes as scheduled, its length gives the shortest possible completion time for the overall project. Activities on the critical path become candidates for crashing, i.e., for reduction in their time by payment of a premium for early completion. Activities on the critical path have zero slack time and conversely, activities with zero slack time are on a critical path. By successively relaxing activities on a critical path, a curve showing total project costs vs. time can be obtained.

CISA Certified Information Systems Auditor – Question2819

To minimize the cost of a software project, quality management techniques should be applied:

A.
as close to their writing (i.e., point of origination) as possible.
B. primarily at project start-up to ensure that the project is established in accordance with organizational governance standards.
C. continuously throughout the project with an emphasis on finding and fixing defects primarily during testing to maximize the defect detection rate.
D. mainly at project close-down to capture lessons learned that can be applied to future projects.

Correct Answer: C

Explanation:

Explanation:
While it is important to properly establish a software development project, quality management should be effectively practiced throughout the project. The major source of unexpected costs on most software projects is rework. The general rule is that the earlier in the development life cycle that a defect occurs, and the longer it takes to find and fix that defect, the more effort will be needed to correct it. A well-written quality management plan is a good start, but it must also be actively applied. Simply relying on testing to identify defects is a relatively costly and less effective way of achieving software quality. For example, an error in requirements discovered in the testing phase can result in scrapping significant amounts of work. Capturing lessons learned will be too late for the current project. Additionally, applying quality management techniques throughout a project is likely to yield its own insights into the causes of quality problems and assist in staff development.