CISA Certified Information Systems Auditor – Question0124

An internal audit department recently established a quality assurance (QA) program. Which of the following activities is MOST important to include as part of the QA program requirements?

A.
Ongoing monitoring of the audit activities
B. Analysis of user satisfaction reports from business lines.
C. Feedback from internal audit staff
D. Long-term internal audit resource planning

Correct Answer: A